IREN’s proposed Redbank data centre development near Wagga Wagga in regional New South Wales is targeting an enormous 600 megawatts (MW) of IT computing capacity. However, a critical question remains over whether the project can secure the electricity supply needed to make it a reality.
The proposed five-building campus, being developed through IREN subsidiary TAS 1 Holdings, could require up to 900 MW of gross electrical capacity, making it one of the largest proposed data centre developments in Australia.
But despite the scale of the proposal, electricity capacity for the development has not yet been secured through Transgrid, highlighting a significant potential obstacle to its delivery.
According to reporting by W.Media on November 22, a project scoping report outlines the proposed electricity requirements and connection infrastructure for the development.
The distinction between the 900 MW gross electricity requirement and the 600 MW IT load is important. The additional electricity would support cooling systems and other essential facility infrastructure.
Based on a design annualised power usage effectiveness (PUE) of approximately 1.3, the report estimates average facility demand at around 780 MW when operating at full IT capacity.
Major grid connection still to be secured
The proposed development site, located in the locality of Rowan near Wagga Wagga, is approximately 2.5 kilometres from Transgrid’s existing 330-kilovolt (kV) Wagga Wagga substation.
The scoping report proposes three new 330 kV feeder bays at the existing substation, along with three underground 330 kV circuits connecting to a new on-site 330/132 kV substation.
The proposed substation would incorporate four 375 megavolt-ampere (MVA) transformers, with four additional 132/33 kV substations distributing electricity to the five data centre buildings.
IREN has indicated it will fund the dedicated connection infrastructure required for the project.
However, the proposed engineering solution should not be confused with an approved or secured electricity supply. No Transgrid capacity allocation has been identified in the reporting, leaving a substantial question over whether the required power can be made available and when.
For a development requiring up to 900 MW, securing sufficient transmission capacity will be one of the most important factors determining whether the project can proceed at its proposed scale.
Planning process at an early stage
IREN first announced the Redbank proposal on October 14, 2026. The development has subsequently been listed on the NSW Planning Portal as a State Significant Development under reference SSD-155572991.
The proposal includes five data centre buildings with total electricity consumption of up to 900 MW, together with an amendment to the Wagga Wagga Local Environmental Plan 2010.
Its current planning status is listed as “Prepare SEARs” (Secretary’s Environmental Assessment Requirements), an early stage of the planning assessment process before preparation of a detailed Environmental Impact Statement.
This means the development remains subject to further planning and environmental assessment, in addition to the unresolved electricity supply arrangements.
Regional opportunity, but power remains the big question
The proposed Redbank campus highlights the growing interest in regional Australia as a destination for large-scale AI and data centre infrastructure.
For Wagga Wagga and the broader Riverina region, a development of this magnitude could create opportunities for investment, construction activity, employment and supporting infrastructure.
However, the project’s potential scale also illustrates the increasing pressure that large data centre developments could place on Australia’s electricity transmission network.
While IREN has outlined an ambitious development and a proposed grid connection solution, securing the necessary electricity supply remains a fundamental requirement.
Until that capacity is confirmed, the proposed 600 MW IT campus remains an ambitious development proposal rather than a project with its power requirements secured.
For now, the biggest question surrounding Redbank is not simply how large the data centre could become, but whether the electricity needed to operate it will actually be available.
Planning a data centre without securing power is lunacy as you need the power to run the servers.