Miners Rest Data Centre: the arguments for and against

A former quarry on the edge of Miners Rest, about 10 kilometres north-west of Ballarat, has become one of the most visible flashpoints in Victoria’s data centre debate. Residents have joined statewide protests, local politicians have called for consultation, and the state’s new rules for data centres are being tested against a project that has not yet lodged a planning application.

This article sets out what is proposed, the case made against it, the case made for it, and what remains unknown.

What is proposed

The project is the Miners Rest Renewable Energy Integration Precinct, planned by property developer Resi Ventures in partnership with ASX-listed smart-infrastructure firm X2M Connect, which announced the partnership in mid-June 2026. The 67-hectare site is at the corner of Victoria Street and Cummins Road.

Industry reports describe a precinct rather than a single building. Plans include a data centre of between 10 and 100 megawatts, a battery energy storage system of more than 10 megawatts, heavy electric vehicle charging, an anaerobic biodigester, hot-house horticulture, and links to regional renewable energy zones.

The approval picture matters. In mid-November the City of Ballarat said that, although council officers had held early conversations with the developer, no formal planning applications had been lodged. The local MP, Martha Haylett, said there was no planning approval, no permits and no meaningful consultation. The council has also noted that recent changes to Victorian planning law could allow the Minister for Planning to decide the project.

The case against development

Consultation and trust. The most consistently made argument is about process. The No Data Centre Miners Rest group says residents learned of the plan through media reports rather than from the developer, and that information has been hard to find. The local MP has said a project of this significance should not be imposed without scrutiny and engagement. A First Nations volunteer firefighter has also said the proposal reflects a lack of care for Country.

Water. Opponents raise two concerns. The first is firefighting: a local CFA volunteer says crews regularly fill tankers from water at the site, and that losing it would increase reliance on the local treatment plant ahead of a fire season forecast to be severe. The second is an aquifer. The group’s secretary says one lies beneath the site and supports farmers downstream, and fears it could be drawn on or contaminated.

Noise and local character. The group says the facility could produce 63 to 65 decibels continuously, audible up to a kilometre away. More broadly, residents argue that a large industrial-scale facility would change the character of a small rural town of under 4,000 people, while delivering little local benefit.

The wider context. The local objections sit inside a statewide movement. Thousands of people rallied outside the State Library of Victoria on 14 November calling for a moratorium on new data centres. In October the Municipal Association of Victoria, which represents all 79 councils, passed a resolution calling for a pause on approvals for new or expanded data centres until a comprehensive planning and environmental framework exists. Hume City Council had unanimously endorsed a similar call in August, and the Greens called for a moratorium on large new data centres in June. Supporters of a pause argue that the framework should come before further approvals, and note that councils say the state planning pathway limits their influence over major projects.

The case for development

A better kind of site. Supporters point out that this is a former quarry, not productive farmland, and that a 67-hectare parcel offers more room for separation from neighbours than most urban data centre sites. The Victorian Government’s new rules aim to steer data centres away from homes, schools and productive agricultural land, and a brownfield industrial site is arguably consistent with that intent.

An integrated energy model. The precinct is designed around on-site and nearby energy infrastructure, including battery storage and renewable connections. That echoes the state’s new requirement that data centres supply their own clean energy and cover additional infrastructure costs, and the developers argue regional precincts are an underserviced opportunity.

Economic and digital benefits. The Victorian Government says the data sector delivered $5.8 billion of capital expenditure in the state last year and supports hundreds of construction jobs. Data centres underpin banking, healthcare, transport and emergency services, and proponents argue that Victoria needs capacity to remain competitive. Spreading facilities beyond Melbourne’s west, where most of the state’s 50 operating centres are concentrated, is also argued to reduce pressure on any single area.

Safeguards are being strengthened. Under the Sustainable Data Centre Action Plan, data centres would be prohibited in residential zones, with a 150-metre buffer between a data centre and homes, and restricted in rural zones unless close to critical infrastructure. They would be barred from using drinking water for cooling. The water corporation, WorkSafe, Fire Rescue Victoria and VicGrid would join the EPA as referral authorities, and the Minister for Planning’s statement of expectations includes public consultation. Industry body Data Centres Australia argues that the existing planning system already assesses actual impacts and imposes conditions site by site, and that heavy new constraints could undermine investment decisions already made.

A pause is a blunt tool. Some commentators argue that a pause is not a rejection of data centres but only buys time, and that the real task is to build better ones. The Victorian Government’s stated approach is guardrails rather than a halt.

What is not yet known

Much of the argument rests on facts that have not been published, which is why claims on both sides should be treated with care.

  • Zoning and distance to homes. Whether the site’s zoning and the distance to the nearest residences satisfy the new prohibition and 150-metre buffer has not been reported.
  • Cooling and water source. No cooling design or water supply has been made public. Closed-loop cooling reduces evaporative water use, but does not automatically mean zero water use. The aquifer concern is a campaigner’s claim, and there is no published evidence either way about whether the project would draw on it.
  • Noise. The 63 to 65 decibel figure comes from a campaigner. It is unclear where it would be measured or what assessment sits behind it, and no acoustic report has been published.
  • Scale. Reports conflict about the building’s size, with one local outlet describing roughly 100 square metres and a campaigner saying up to 350 metres long.
  • The developer’s position. The ABC said it had contacted Resi Ventures for comment, and I could not find a published response addressing the water, noise or consultation claims.
  • Rules still settling. Some of the state’s new requirements were presented as proposals or as commitments of a re-elected government, and are said not to apply to projects already being assessed. Because no application has been lodged here, they would probably apply, but their final form depends on implementation.

The state election this month may shape which approach prevails, though the outcome is not yet known.

Where this leaves the debate

The case against is strongest on process: residents say they were not consulted, and the developer has not publicly answered their questions. The case for is strongest on siting and design principles, but those arguments are largely untested because there is no application, no technical report and no published design. The decisive evidence is likely to be a planning application, with its water, noise and bushfire assessments, and the answers of the referral authorities. Until then, both sides are arguing about a project whose detail the public has not seen.

Sources

ABC News (Ballarat), 16 November 2026, on the rally and local concerns; The Courier (Ballarat), July and November 2026; The West Vic Brolga, 16 July 2026; IT Brief Australia, 17 June 2026; DatacenterDynamics, on the X2M and Resi partnership; VibeWire, 21 November 2026; Victorian Government Sustainable Data Centre Action Plan and the Minister for Planning’s statement of expectations, September and October 2026, with coverage from The Urban Developer, Hall & Wilcox and The New Daily; ABC News, 30 October 2026, on the Municipal Association of Victoria resolution; Hume and Melton City Council statements; Schneider Electric Australia commentary on closed-loop cooling, August 2026.