Plans for the next major phase of Oxford station’s transformation are moving forward, with a new platform and western entrance planned to create more space for train services and make the station easier for passengers to use.
Network Rail is progressing plans for a new through platform and an additional entrance on the western side of the station, with both currently targeted to open by summer 2029, subject to funding being released and the main construction contract being awarded.
The improvements are designed to help Oxford station meet growing demand in the years ahead, including supporting potential future services linked to East West Rail, the reopening of the Cowley Branch Line and other developments in and around the city.
Design work on the new western entrance has restarted and is being updated to reflect the latest forecasts for passenger numbers, including travel associated with East West Rail and the Universal Resort in Bedfordshire. The design is expected to progress through the planning process by mid-2027.
Current proposals for the western entrance include ticket machines, ticket gates and toilets, with cycle parking and areas for passenger pick-up and drop-off also being considered.
Tom Pierpoint, industry programme director for Network Rail’s Great Western route, said: “The new platform and western entrance are a really important part of preparing Oxford station for the future, giving passengers another way in and out of the station while creating the extra capacity needed to support more train services.
“We know delivering the next phase of the upgrade will have an impact locally, particularly around Roger Dudman Way. We’re looking carefully at how we can reduce that disruption and will keep residents and businesses informed as the plans develop.”
Under the indicative programme, Roger Dudman Way would need to close to through traffic for around 20 months to allow major construction work to take place.
Pedestrian and cycle access would be maintained, while a diversion route would also be put in place for vehicles requiring local access.
The closure would allow teams to build new road and rail bridges at Sheepwash and safely divert utility pipes and cables. The plans include a road diversion to the north and a temporary footbridge to maintain access to and from Roger Dudman Way.
Network Rail is working with its contractors and partners to identify ways of reducing the length and impact of the closure, including carrying out some activities around the clock where appropriate. Further information for residents, including details of piling and other construction activity, will be shared once the programme has been finalised.
Botley Road and its pedestrian walkways are expected to remain open throughout the remaining work.
Ahead of this next stage of station improvements starting, work on the previous stage is being completed, including completing the temporary junction from Cripley Road to Roger Dudman Way, replacing temporary railings with permanent, and repairing paving in Frideswide Square. Work on the new southern walkway along Botley Road is taking place overnight to minimise disruption.
The new western entrance and platform form part of a wider ambition to improve Oxford station and the surrounding area.
Separate longer-term proposals include a potential new eastern entrance, a cycle hub, better connections with other forms of transport, improvements to public spaces and development around Beckett Street.
Public consultation on these wider proposals is provisionally planned for late May to early July 2027.
Network Rail also plans to hold regular stakeholder update sessions during 2027, alongside updates through newsletters, its website, Facebook and direct letters to people affected by the work.
Residents and businesses can contact the project team at OxfordFeedback@networkrail.co.uk.