The Johor state government has released figures to address growing concerns that the rapid expansion of data centres could place significant pressure on the state’s water resources and threaten household supplies.
According to figures presented in the state assembly on Friday (20 November), the 19 data centres currently operating in Johor account for just 1.05% of the state’s total treated water output, based on their approved daily water allocation.
The state government also dismissed claims that data centres were responsible for declining water levels at several dams, stressing that the facilities do not receive water from the dams in question.
According to The Star and Nanyang Siang Pau, Johor executive councillor for public works, transport, infrastructure and communications Mohamad Fazli Mohamad Salleh disclosed the figures in response to questions about the data centre industry’s impact on the state’s water and electricity resources.
Fazli said the 19 operating data centres had initially applied for a combined water allocation of 73.088 million litres per day. However, only 21.277 million litres per day was eventually approved.
This represents approximately 1.05% of Johor’s total treated water output of 2.034 billion litres per day, and 3.35% of the state’s total industrial water consumption of 635 million litres per day.
While the figures indicate that data centres are not currently a major contributor to pressure on Johor’s water supply, Fazli said the state government remained cautious about rising demand from the industry.
He emphasised that continued monitoring would be necessary to ensure future developments do not compromise water availability for domestic consumers.
Drought, Not Data Centres, Behind Falling Dam Levels
Addressing concerns over declining water levels at several dams, Fazli described attempts to link the situation to data centre operations as a misrepresentation of the facts.
He said water levels at the six dams currently under close monitoring — Machap, Lebam, Gunung Pulai II, Pontian Kechil, Upper Layang and Lower Layang — had fallen primarily because of prolonged dry weather and the effects of El Niño.
These climatic conditions are expected to persist until March next year.
Fazli also clarified that none of the six dams supplies water to Johor’s operating data centres.
Machap and Lebam dams do not serve any data centre facilities, while Gunung Pulai II and Pontian Kechil dams primarily supply consumers in the Pontian area.
Meanwhile, Upper Layang and Lower Layang dams provide water to households and industrial users in Pasir Gudang, Plentong, Pandan and Taman Daya.
In contrast, the state’s 19 operating data centres receive most of their water from the Semangar and Sungai Johor water treatment plants, both of which draw raw water from the Johor River.
Fazli said the different water supply arrangements meant that declining storage levels at the six dams should not be directly attributed to data centre operations.
Stricter Assessment and Water-Efficient Technologies
Beyond addressing current water consumption, the Johor government has also introduced measures to ensure that future data centre developments do not place excessive demands on the state’s resources.
Fazli said a Data Centre Development Coordination Committee, comprising 20 state and federal agencies, was established in 2024 to oversee and assess proposed projects.
All new developments must undergo a comprehensive evaluation of available water and electricity capacity, green technology adoption, and water and energy efficiency before proceeding with applications for planning permission from local authorities.
The state government also requires data centre operators to adopt cooling systems designed to minimise water consumption, including air-cooled chillers, direct-to-chip liquid cooling and immersion cooling technologies.
Of Johor’s 19 operating data centres, nine have already adopted these water-saving cooling technologies.
In terms of daily consumption, 11 facilities use less than one million litres of water each, while the remaining centres consume between one million and 4.17 million litres per day.
The state government’s latest figures suggest that, although data centres currently account for a relatively small proportion of Johor’s treated water output, managing the industry’s growing resource requirements will remain an important consideration as the state continues to attract investment in the digital infrastructure sector.