The last tunnel boring machine active in the construction of the Brenner Base Tunnel reached its destination, marking “the completion of all mechanised excavation works”, BBT said. With Olga’s ‘retirement’ the excavation of the two main tubes is now completed.
Olga follows its ‘sister’ Wilma, which completed the excavation of the western tunnel in August. Both TBMs had been digging the 7.6 kilometres in each tube along the Pfons-Brenner lot since 2024.
Opening date moved
Despite the good news, BBT recently announced that the whole project will require more time and more money. Instead of 2032, the Brenner Base Tunnel will be ready in 2034, with its costs growing from €10.5 to €11.7 billion. The delay and higher costs are mostly due to the decision of turning one of the exploratory tunnels into a service one.
Now, the two main tubes need to be ‘dressed’ and transformed into proper railway lines. Once ready, the Brenner Base Tunnel will connect Fortezza with Innsbruck across the Italian-Austrian border. This is a key section of the Verona-Munich line and the Scandinavian-Mediterranean TEN-T corridor, of the busiest European logistics axis.