Georgian Railway has launched an international tender for the construction of a new line to the Anaklia deep-sea port. The 17.7-kilometre electrified connection is estimated to cost around $205 million (about €183 million) and will be built with financial support from the World Bank.
National rail operator Georgian Railway wants to connect the future port on the Black Sea coast directly to its network. The new line will branch off the existing mainline near the village of Khamiskuri and run to the port of Anaklia. Besides the line itself, the project includes a new station in Anaklia and the reconstruction of the infrastructure at Khobi station.

The contractor will have 30 months from the signing of the contract to complete the work. The schedule is designed so that the rail infrastructure is ready by the time the port starts operations in 2029, Georgian Railway said.
The tender comes a little later than the government had promised. On 9 October, Georgian Prime Minister Irakli Kobakhidze said the construction tender would be announced by the end of October. The bidding deadline is not yet known.
Middle Corridor ambitions
Georgian Railway has characterised the project as strategically important for the country’s transport system. A direct rail connection should enable efficient freight handling and uninterrupted transport, and allow the port to use its full capacity, the company explained in its statement. Moreover, developing the port and the railway together would “strengthen the country’s position along the Middle Corridor” and help attract more international transit between Europe and Asia, it added.
The port itself is being built to receive some of the largest vessels operating in the Black Sea. Dredging should deepen the seabed in the port area to approximately 17.5 metres, and the plans include a 1,376-metre breakwater.