Passenger Service Resumes in San Clemente; OCTA Seeking Long-Term Solutions

SAN CLEMENTE – Two months after a landslide halted passenger service at Mariposa Point, OCTA announces the completion of a catchment wall has allowed regular passenger service to resume.
The post Passenger Service Resumes in San Clemente; OCTA Seeking …

Completion of Catchment Wall Allows Passenger Service To Resume in San Clemente

ORANGE COUNTY – Crews finished work on the 200-foot-long catchment wall that will protect the rail right of way in San Clemente. This comes after a landslide caused passenger service to halt in January.
The post Completion of Catchment Wall Allows Pass…

OCTA Continues Coastal Rail Resiliency Study; Catchment Wall Wooden Panels Now Up

ORANGE COUNTY – As OCTA and Metrolink work to address a stretch of the rail line after a landslide in January, it seeks longer-term solutions for protecting the rail right of way.
The post OCTA Continues Coastal Rail Resiliency Study; Catchment Wall Wo…

Catchment Wall Construction Begins in San Clemente

SAN CLEMENTE – Two large rigs began drilling so steel beams can be placed 30 feet underground to support the catchment wall in San Clemente.
The post Catchment Wall Construction Begins in San Clemente appeared first on Railway Track and Structures.

OCTA Awarded $7.2M for Barrier Wall; Slope Movement Accelerates

SAN CLEMENTE, Calif. – Freight traffic halted once more after crews observed accelerated movement of the slope in San Clemente, and OCTA received $7.2 million for a catchment wall.
The post OCTA Awarded $7.2M for Barrier Wall; Slope Movement Accelerate…

OCTA and Metrolink Continue Work; Metrolink Issues RFP

ORANGE COUNTY – OCTA and Metrolink crews have removed some tarps to assess the condition of the slope. Metrolink issues RFP to construct a barrier wall.
The post OCTA and Metrolink Continue Work; Metrolink Issues RFP appeared first on Railway Track and…

OCTA Update; Still Pursuing Barrier Wall After Heavy Rain

SAN CLEMENTE – As debris continues to fall near Mariposa Point, OCTA gives an update on the rail right-of-way.
The post OCTA Update; Still Pursuing Barrier Wall After Heavy Rain appeared first on Railway Track and Structures.

OCTA and Metrolink Will Construct Barrier Wall in San Clemente

SAN CLEMENTE – To prevent debris from falling on the track, crews will construct a barrier wall along the rail line in Orange County.
The post OCTA and Metrolink Will Construct Barrier Wall in San Clemente appeared first on Railway Track and Structures…

San Clemente Landslide Update; Upcoming Storm System, Continued Hillside Movement

SAN CLEMENTE, Calif. – OCTA gives an update on the San Clemente landslide, and an incoming storm system will bring additional rainfall and increase the risk of a mudslide in the area.
The post San Clemente Landslide Update; Upcoming Storm System, Cont…