The French rail infrastructure manager SNCF Réseau has signed a rail performance contract with the national government. By 2033, France should have modernised infrastructure that can accommodate more trains. Dedicated goals for freight are included, but do real targets match the stated ambitions?
The performance contract envisages the number of trains operating on the network to grow by 25% in 2033 compared to 2024. That would equal nearly 800,000 additional high-speed, regional and freight trains. Annual rail spending will rise substantially, although it is not yet clear where all those funds will come from.
RailFreight.com covered the financial question earlier, so let’s look at capacity targets instead. The contract describes a strong expected improvement for freight trains. If France is to modernise its infrastructure, there will also be more temporary capacity restrictions. Freight is among the most affected by infrastructure works.
Despite the growth targets and recognised scope for improvement, the contract envisions a stabilisation in the percentage of paths allocated at a worse level. In 2025, France allocated 91.8% of all requested freight train paths. From 2028 onwards, this is meant to remain at 90.5% until 2033. Effectively a step backwards.

Weaker rail freight predictability target
Moreover, SNCF Réseau commits to a more relaxed train-path modification target. The infrastructure manager will try to restrict its timetable changes to a maximum of 1.9% of freight path-days (defined as one path counted once for each day it runs) after the timetable is certified. A freight path only counts as changed if it moves by more than 30 minutes. For passenger paths, the boundary is 5 minutes. In 2024, SNCF Réseau aimed to keep the modification figure below 1.7%.
Lastly, around a fifth of capacity reserved for construction works sits idle. In other words, one in five infrastructure construction windows goes unused and trains could have run instead. This share grew from 19% in 2025 to an expected 21% in 2026. The newly established target wants to reduce this to 10% by 2030 and stabilise it at that level.
An investment without money?
The fulfillment of these targets will depend on funding for the investment programme. SNCF Group has agreed to carry one-third of the investment increase. This equals €500 million per year. Still, it remains unclear who will pick up the bill for the remaining additional spending of €1 billion. The investment plan comes at a time when France’s public debt has reached gigantic proportions. Consequently, the government is under severe pressure to exercise budgetary restraint.
The governance of freight train paths is also subject to change. The EU’s Capacity Regulation provides a new legal framework: from December 2030, it requires infrastructure managers to publish planned works years ahead in their capacity plans, so freight operators know which paths will be affected. For major works, operators can demand alternative capacity, including on diversionary routes. If construction works force a change to an allocated path, SNCF Réseau must offer an alternative and pay a penalty for significant changes. Detailed rules are still being drafted.